ID23-1 Updates

last modified 12-09-2007 07:38

 

Medium Size Logo

 

 

2002

    • 1 January ID23 received first round funding
    • 5 March Detailed floor plans completed and signed
    • 20 December Cabins and lead hutches completed

 

2003

    • 12 February optical hutch radiation test completed
    • 11 March installation of the primary slits completed
    • 23 May first X-ray beam in the optic hutch (primary slits commissioning)
    • 20 June experimental hutch radiation test completed
    • 25 October first data set collected
    • 5 November toroidal miror installed

 

2004

    • 12 March diffractometer installed and prealigned
    • 16 March slit box installed and aligned

 

2005

    • 18 January final toroidal mirror installed
    • 12 January installation of the final detector translation
    • 11 April installation of the fast piezo shutter
    • 25 August installation automatic sample changer
    • 3 October installation of the ADSC Q315 detector

 

2006

    • 13 June Zap EXAFS scans


Further information about the station is available from us.