2002

  • 1 January ID23 received first round funding
  • 5 March Detailed floor plans completed and signed
  • 20 December Cabins and lead hutches completed

 

2003

  • 12 February optical hutch radiation test completed
  • 11 March installation of the primary slits completed
  • 23 May first X-ray beam in the optic hutch (primary slits commissioning)
  • 20 June experimental hutch radiation test completed
  • 25 October first data set collected
  • 5 November toroidal miror installed

 

2004

  • 12 March diffractometer installed and prealigned
  • 16 March slit box installed and aligned

 

2005

  • 18 January final toroidal mirror installed
  • 12 January installation of the final detector translation
  • 11 April installation of the fast piezo shutter
  • 25 August installation automatic sample changer
  • 3 October installation of the ADSC Q315 detector

 

2006

  • 13 June Zap EXAFS scans

 